Bike Rack Program Timeline and Funding

Update on Current Bicycle Requests

In 2013 the City of Berkeley received an allocation of $150,000 from the Transportation Fund for Clean Air from the Bay Area Air Quality Management District.  This funding is for the installation of bike racks and six new in-street "bike corral" high capacity bike parking areas (locations TBD) during 2014 and 2015.  The City currently has a bike corral located on Kittredge Street in front of the Downtown Branch of the Berkeley Public Library.  Following this next round of installations, the City is planning a second allocation of $180,000 from TFCA for more bike racks and 12 additional bike corrals in a subsequent construction project.

The City currently has approximately 115 bicycle rack locations in the queue to be installed.  If you requested a bicycle rack, your request will be installed based on when it was received.  Please see the schedule below:

Fiscal Year 2014/2015 Schedule: 
    June - July 2014:  Prepare bid documents and advertise bike rack installation project for construction     

    July 1, 2014 - Cutoff date for new bike rack requests.  All racks requested on or before this date will be installed as part of

        the 2014-2015 Program        

    August 2014 - September 2014:  Open bids, execute contract documents, issue Notice to Proceed,

        hold preconstruction meeting

    October 2014 - November 2014: Quality control/quality assurance; bike rack samples inspection; place bike rack order

    November 2014 - December 2014: Bike rack fabrication and shipping

    December 2014 - March 2015: Install bike racks (in priority order to be determined by Transportation

        Division of Public Works)

    January 2015 - March 2015: Install bike corrals

Fiscal Year 2015/2016 Annual Bike Rack Installation Project Schedule:
    July 2015-August 2015: Prepare bid documents and advertise bike rack installation project for construction

    December 1, 2015 - Cutoff date for new bike rack requests.  All racks requested on or before this date will be installed as part

    of the FY 2015/2016 Program

    September 2015 - October 2015: Open bids, execute contract documents, issue Notice to Proceed,  

        hold preconstruction meeting

    January 2016 - March 2016:  Install bike racks and bike corrals (in priority order to be determined by Transportation

        Division of Public Works)

For additional questions about the next round of bicycle rack installations, please contact Eric Anderson at eanderson@cityofberkeley.info or 510-981-7062.

The City's Bicycle Parking Program is supported by Alameda County Measure B sales taxes and grants from the Bay Area Air Quality Management District Transportation Fund for Clean Air.

Home | Web Policy | Text-Only Site Map | Contact Us
Transportation Division, 1947 Center Street, 4th Floor, Berkeley, CA 94704
Questions or comments? Email: transportation@cityofberkeley.info Phone: (510) 981-7010
(510) 981-CITY/2489 or 311 from any landline in Berkeley
TTY: (510) 981-6903
###