Currently Funded Capital Projects List

Projects Under or Soon to be Under Construction  

Berkeley Tuolumne Camp Pre-Construction Projects

  • Tree Removal, In Construction
  • Cultural Resources Protection, Construction Sept
  • Existing Building Repair, Construction Oct.

Citywide Irrigation System Replacement - In Construction
George Florence Park – Play Structures Renovation - In Construction Sept. 
Harrison Fields Renovation, In Construction 
James Kenney Park and Play Equipment - In Construction, Oct./Nov
John Hinkel Upper ADA Pathway and Picnic Area - In Construction, October/Nov.
Live Oak Community Center Seismic, ADA Upgrades, In Construction, October 
 Ohlone Park Courts, In Construction
Rose Garden Pergola, Tennis Courts, ADA pathways, Creek Improvements - In Construction, Jan.
Waterfront Finger Dock - Construction Nov/Dec.
Waterfront-South Cove Small Dock Replacement - Construction, October/Nov
Waterfront South Cove Gangway Replacement - Construction, October/Nov
Waterfront- Bay Trail Extension Phase 3 - Construction, October/Nov
Waterfront Corp Yard Electrical - In Construction, October

Construction Projects in Design  

Aquatic Park Tide Tubes Clean/out/Design
Aquatic Park Rowing Club Parking Lot/ dock area
Aquatic Park South PathwaysCamps- Echo Lake Camp Leach Fields
Camps-Cazadero Camp Dormitory Replacement
Camps-Echo Lake Camp ADA Pathways, Tent Cabin Addition 
Camps-BTC Construction
Grove Park Phase 2 - Field and Restroom Renovation
Harrison Park - Skate Park Fence Replacement 
John Hinkel Lower Play Structures & Amphitheater
King School Park Renovation 2-5 Play Area
Ohlone Park - TBA
Pools - West Campus, filter replacement
San Pablo Park – (5 -12) Play Structure  
San Pablo Park – (2 - 5) Play Structure
San Pablo Park Tennis Courts Renovation
Strawberry Creek Play Structure, Pathway & Restroom Replacement
Waterfront - O & K Dock, Electrical Replacement
Waterfront Restroom Upgrades
Waterfront - Piling Replacement 
Waterfront- University Avenue/ Marina Blvd/ Spinnaker Ave Replacement 

Design Only Projects in Process   

Citywide Restroom Assessment
Frances Albrier Community Center Design
Tom Bates Sports Complex Restroom, Storage, Community Space Design
James Kenney Basketball, Tennis and Entrance Area Design
Waterfront-Berkeley Pier Analysis and Conceptual Design - Phase 3 
Waterfront – Sea Level Rise Study
Waterfront- Berkeley Marina Area Specific Plan (BMASP) 
Willard Clubhouse Design

Recently Completed Projects

2019

Becky Temko Play Area 
Camps-Berkeley Tuolumne Camp Design/Planning & Environmental Process 
Cedar Rose Courts/Ohlone Greenway Improvements
Echo Lake Camp Snow Damage
Glendale-La Loma Basketball Court 
San Pablo Restroom Building Renovation 
Strawberry Creek Court Replacement, Phase 1
Waterfront Corp Yard Electrical 
 Waterfront Rip Rap Replacement (Eastern side)

2018

Camps-Cazadero Camp Landslide Fix- Construction
Camps-Echo Lake Leach Field Replacement/restroom repairs 
Gilman Artificial Turf Field Replacement- Construction  
Grove Park Basketball and Tennis Courts
Pools-West Campus Pool Boiler Replacement
Marin Fountain-Sewer, Equipment Door, Landscaping
Waterfront-South Cove East Parking Lot/Restroom Addition 
Waterfront-Bait Shop Siding/Structural Beam Replace
Waterfront-Parking Gate and Barrier at Launch Ramp  

2017

Bahia Child Care Center Seismic, Siding and ADA upgrades 
Camps-Berkeley Tuolumne Camp Conceptual Design 
Camps- Cazadero Camp Tree Removal/ Building Demo/ Temp. Stabilization 
Camps- Echo Lake Camp Emergency Facility Repairs- snow damage 
James Kenney Community Center Seismic, Siding and ADA
Pools:  King Pool Boiler Replacement 
Rose Garden Pergola, ADA Phase 1 
Skate Park Safety Improvements and Technical Upgrades 
Willard Park - Play Area and Pathways 

2016

Ohlone Dog Park 
Terrace View Phase 1 
Totland – Virginia McGee  
Willard Park Tennis Courts
Pools:  King Pool Filter Replacements 

 

Home | Web Policy | Text-Only Site Map | Contact Us
Parks Recreation & Waterfront Department, 2180 Milvia Street, Berkeley, CA 94704
Questions or comments? Email: parks@cityofberkeley.info Phone: (510) 981-6700
(510) 981-CITY/2489 or 311 from any landline in Berkeley
TTY: (510) 981-6903
###